Good afternoon Severn House, please view and make notes of the following updates.
Power Washing
– The decks for building 2 will receive two coats of stain today. The paint will take 2 days to properly cure and dry.
– The decks for building 3 will be powerwashed starting Monday, May 23rd . Staining for building 3 will start Wednesday or Thursday (weather permitting). It will take 3-4 days to complete the entire building with the same 2-day dry time.
Deck Post Replacement
– The deck posts on building 1 will be completed by Friday.
– Building 2 will be completely Monday -Friday of next week.
– Chinquapin will then follow the powerwashing and staining for building 3, and complete the posts on that building during the last week of May.
**All Exterior Work is Weather Permitting. Expect delays with bad weather**