  Good afternoon Severn House, please view and make notes of the following updates.  

Power Washing

–  The decks for building 2 will receive two coats of stain today.  The paint will take 2 days to properly cure and dry.  

– The decks for building 3 will be powerwashed starting Monday, May 23rd .  Staining for building 3 will start Wednesday or Thursday (weather permitting).  It will take 3-4  days to complete the entire building with the same 2-day dry time. 

Deck Post Replacement

– The deck posts on building 1 will be completed by Friday.

– Building 2 will be completely Monday -Friday of next week.  

– Chinquapin will then follow the powerwashing and staining for building 3, and complete the posts on that building during the last week of May.  

**All Exterior Work is Weather Permitting.  Expect delays with bad weather**